Community
Participate
Working Groups
3.0 RC2 I the keepone property is to work as designed, it will have to be updated at the end of the job. We use the property to indicate is the progress viewer should keep the job task info in the view after the job as completed. We have decided that synchronize jobs should be kept if run in the background, and not kept if run in the foreground. Our synchronize job is currently only setting the property when created which is causing all synchronize jobs to be added to the view.
I would like to consider for 3.0. Low risk and easy fix.
+1 for RC3.
Created attachment 12475 [details] patch Easy fix, two lines- 1. use of api keepone constant that was introduced yesterday instead of internal class 2. setting keepone at the end of the job so that if the user progress dialog was dismissed, the job is not kept in the progress view.
released.