Plan Mylyn 3.9.1 release: http://www.eclipse.org/projects/project-plan.php?projectid=mylyn .
I updated all versions to 3.9.1. I'll publish a weekly build in a few days after Kepler is out to make Gerrit connector fixes available.
As discussed during today's call, a release at the end of July would be desirable to make Gerrit connector fixes and Gerrit 2.6 support available. I would propose July 31 as a target date.
We didn't fully finish the fixes for Gerrit 2.6 and some important defects weren't resolved as of July 31 so we discussed moving the release date to August 28 on today's call. I have updated the calendar accordingly and moved some of the less important bugs to the 3.9.2 milestone.
The final build for 3.9.1 is up on the snapshot site: http://download.eclipse.org/mylyn/snapshots/3.9 . It will be released as part of Kepler SR1 in 2 weeks on September 27.
The release is now available.