Some Eclipse Foundation services are deprecated, or will be soon. Please ensure you've read this important communication.
Bug 348520 - "Synchronize" on a day in "Scheduled" mode does nothing
Summary: "Synchronize" on a day in "Scheduled" mode does nothing
Status: RESOLVED FIXED
Alias: None
Product: z_Archived
Classification: Eclipse Foundation
Component: Mylyn (show other bugs)
Version: 3.6   Edit
Hardware: PC Windows XP
: P3 minor (vote)
Target Milestone: 3.7   Edit
Assignee: Frank Becker CLA
QA Contact:
URL:
Whiteboard:
Keywords:
Depends on:
Blocks:
 
Reported: 2011-06-07 04:42 EDT by Tomasz Zarna CLA
Modified: 2011-06-09 16:11 EDT (History)
1 user (show)

See Also:


Attachments

Note You need to log in before you can comment on or make changes to this bug.
Description Tomasz Zarna CLA 2011-06-07 04:42:30 EDT
Eclipse I20110603-0909
Mylyn 3.6.0.I20110531-2141

1. Open "Task List"
2. Switch to "Scheduled" mode
3. Right click on any day and select "Synchronize"
=> SHOULD BE: all tasks planned for the given day should be synchronized
=> IS: nothing happens, I need to switch to regular mode and sync tasks by queries
Comment 1 Steffen Pingel CLA 2011-06-07 09:21:27 EDT
Thanks for the bug report. I agree that the Synchronize menu item should either work or be hidden.
Comment 2 Tomasz Zarna CLA 2011-06-07 11:34:26 EDT
+1 for "work", if you want to know my opinion ;)
Comment 3 Frank Becker CLA 2011-06-09 16:11:43 EDT
only the following object types are supported

- IRepositoryQuery
- TaskCategory
- ITask

I add
- ScheduledTaskContainer
- Person
- TaskGroup