Summary: Indigo freeze plan
Product: [Eclipse Project] Platform Reporter: John Arthorne <john.arthorne>
Component: PMCAssignee: John Arthorne <john.arthorne>
Status: RESOLVED FIXED QA Contact:
Severity: normal    
Priority: P3 CC: daniel_megert, jeffmcaffer, Mike_Wilson, mober.at+eclipse, remy.suen
Version: 3.7   
Target Milestone: 3.7 M7   
Hardware: All   
OS: All   
Whiteboard:

Description John Arthorne CLA 2011-03-29 13:40:05 EDT
We need a freeze plan for the Indigo release.
Comment 1 Dani Megert CLA 2011-03-31 03:07:18 EDT
Some input taken from http://wiki.eclipse.org/Eclipse/Helios/Retrospective:
- Dates (milestones, RCs) worked well 
- 2 day test pass against RC2 too late ⇒ should be earlier, e.g. afterM7/RC0 

Swiss Public Holidays during freeze phase:
- June 2 (Thursday)
- June 13 (Monday)
Comment 2 John Arthorne CLA 2011-03-31 13:38:47 EDT
Initial draft here:

http://www.eclipse.org/eclipse/development/plans/freeze_plan_3.7.php

This moves the two day test pass to the first two days of RC1 (immediately after M7 is declared). Feedback welcome.
Comment 3 John Arthorne CLA 2011-04-13 13:05:31 EDT
The plan has been posted.