Description
John Arthorne
Some input taken from http://wiki.eclipse.org/Eclipse/Helios/Retrospective: - Dates (milestones, RCs) worked well - 2 day test pass against RC2 too late ⇒ should be earlier, e.g. afterM7/RC0 Swiss Public Holidays during freeze phase: - June 2 (Thursday) - June 13 (Monday) Initial draft here: http://www.eclipse.org/eclipse/development/plans/freeze_plan_3.7.php This moves the two day test pass to the first two days of RC1 (immediately after M7 is declared). Feedback welcome. The plan has been posted. |