Summary: Process usage is shown in HTML output only for tasks with a role attached
Product: z_Archived Reporter: streit
Component: EPFAssignee: Bingxue Xu <bxu>
Status: RESOLVED WORKSFORME QA Contact:
Severity: normal    
Priority: P3 CC: bxu
Version: unspecified   
Target Milestone: ---   
Hardware: PC   
OS: Windows 2000   
Whiteboard:
Attachments:
Description Flags
Method library to reproduce bug
none
Resulting output from publishing Library1 - bug can be seen there none

Description streit CLA 2010-08-12 16:28:06 EDT
Build Identifier: Version: 1.5.0.4

When publishing content with the option "Publish process usage in role, task and work product pages linking to related descriptors" checked, the process usage is shown on the task page only if the task has a role attached.

Reproducible: Always

Steps to Reproduce:
1. Create a config that contains a view with a list of tasks and a list of processes. Create a process and a role.
2. Create two tasks; attach the role to the first of them.
3. Include both tasks in the process.
4. Publish with option "Publish process usage in role, task and work product pages linking to related descriptors" checked.
5. Process usage is shown on the task detail page only for the first task.
Comment 1 streit CLA 2010-08-12 16:29:09 EDT
Created attachment 176503 [details]
Method library to reproduce bug
Comment 2 streit CLA 2010-08-12 16:30:00 EDT
Created attachment 176504 [details]
Resulting output from publishing Library1 - bug can be seen there
Comment 3 Bingxue Xu CLA 2010-08-22 23:43:16 EDT
Could you please try the EPF Composer 1.5.1 nightly build to see if the issue reported still exisits or not?

Thanks very much.
Comment 4 streit CLA 2010-08-23 13:48:54 EDT
Hi,
it seems to work now. Thanks for the fast reaction!
Greetings Jonathan
Comment 5 Bingxue Xu CLA 2010-08-23 14:29:25 EDT
Thanks very much for the confirmation.