Bug 320122

Summary: [Done] Tycho
Product: Community Reporter: Wayne Beaton <wayne.beaton>
Component: Proposals and ReviewsAssignee: Eclipse Management Organization <emo>
Status: RESOLVED FIXED QA Contact:
Severity: normal    
Priority: P3    
Version: unspecified   
Target Milestone: ---   
Hardware: PC   
OS: Linux   
URL: http://eclipse.org/proposals/tycho
Whiteboard:

Description Wayne Beaton CLA 2010-07-16 12:06:58 EDT
A creation review has been requested for Tycho. Project lead has requested that we use the proposal document for the creation review.

Steps required:

1. Verify that community concerns have been addressed;
2. Initiate trademark review (assign any existing trademark to Eclipse);
3. Verify that proposal has the support of two Architecture Council Mentors;
4. Verify that the PMC approves;
5. Verify that the review documentation is complete; and
6. Schedule Review
Comment 1 Wayne Beaton CLA 2010-07-16 17:26:33 EDT
After taking a quick look at the project forum, I am concerned that the community has not been responsive to this proposal. My sense is that there is a community around this project (anecdotally based on messages I see in other forums and mailing lists), so I need to do a little more digging to find the touch points between the existing project and the community.

I have asked the rest of the Technology PMC for their input.
Comment 2 Wayne Beaton CLA 2010-07-16 17:31:20 EDT
I have requested a trademark search/review and that the IP Team work with the project lead to transfer the Tycho name to Eclipse.
Comment 3 Wayne Beaton CLA 2010-07-19 16:07:48 EDT
PMC Approves

http://dev.eclipse.org/mhonarc/lists/technology-pmc/msg02574.html

We are currently waiting on the trademark review.
Comment 4 Wayne Beaton CLA 2010-08-04 16:45:28 EDT
Trademark search and reassignment has been approved. Creation scheduled for August 11/2010.
Comment 5 Wayne Beaton CLA 2010-08-11 11:22:15 EDT
Creation review successful. Project lead has been notified, database has been updated. Waiting for provisioning.
Comment 6 Wayne Beaton CLA 2010-08-11 13:23:15 EDT
NPPR has been received.
Comment 7 Wayne Beaton CLA 2010-08-17 11:14:35 EDT
Project is provisioned. Databases are up-to-date. Marking as FIXED.