Description Derek CLA 2009-12-16 09:25:28 EST
Build Identifier: 20090920-1017

Would be very helpful to see the team estimated time in the popoup. Currently it only shows the private time estimate. We dont use the private estimate. We only use the team estimated time. Everyone on our team needs to know how long a task is going to take so that we can coordinate our tasks. So, seeing the private estiamted time is nice, but not helpfull for us. Maybe in the popup it could have "Estimate: 1 hours/2 hours" where the first is the private and the second is the team.

Reproducible: Always

Steps to Reproduce:
1. Put your mouse over a task in the task list.
2. The popup will show up with the private estimate only.
Comment 1 Frank Becker CLA 2009-12-25 16:10:18 EST
Sorry,

I did not know a team estimated time in Bugzilla. Is this a custom field?
Comment 2 Steffen Pingel CLA 2010-01-04 13:27:06 EST
I assume that this refers to the estimate in the team section (if time tracking is enabled). Unlike due dates, private and team estimates are currently not synchronized. I don't think that we would support showing different types of estimates in the tooltip as this would be confusing but we could support this through synchronizing the values. 

Derek, I'll mark this as a duplicate of bug 212108. Please reopen if the proposed solution would not satisfy your request.

*** This bug has been marked as a duplicate of bug 212108 ***