| Summary: | [Progress] Link from progress view does not bring up synchronization | ||||||
|---|---|---|---|---|---|---|---|
| Product: | [Eclipse Project] Platform | Reporter: | Eugene Kuleshov <ekuleshov> | ||||
| Component: | Team | Assignee: | Platform Team Inbox <platform-team-inbox> | ||||
| Status: | VERIFIED FIXED | QA Contact: | |||||
| Severity: | normal | ||||||
| Priority: | P3 | CC: | dj.houghton, Michael.Valenta | ||||
| Version: | 3.2 | ||||||
| Target Milestone: | 3.2 RC2 | ||||||
| Hardware: | PC | ||||||
| OS: | Windows 2000 | ||||||
| Whiteboard: | |||||||
| Bug Depends on: | 137938 | ||||||
| Bug Blocks: | |||||||
| Attachments: |
|
||||||
|
Description
Eugene Kuleshov
Created attachment 32935 [details]
Example of the progress view
*** Bug 126713 has been marked as a duplicate of this bug. *** In RC2, I no longer even get the links. This could be due either to how we set the action (i.e. we do it in the jobs run before it completes) or to the fact that we ae using a progress group (which we also did in 3.1 which worked). The links are working now due to the fix for Bug 137938 Fixed Verified |